Ajish Daniel when we introduced SPI, we've got blocked on CPI because Teamhood does not have a dedicated default field for cost tracking. Maybe we should allow users to pick which field represents cost…
Maybe you have suggestions how should we do it? Because for planned value we can easily use budget, but factual/actual cost value is missing.
Ajish Daniel
•
Nov 26, 2024
Vidas You could introduce the actual cost field on the Gantt chart just like how I do it using custom fields for both Actual Cost and CPI.
However, one other thing that I have noticed that SPI is calculated based on actual start date and actual finish date in the schedule section. But if I start my activity earlier than the scheduled date and I have some progress on the task it won't show any SPI as well. Attached is the reference.
Vidas
Team•
Nov 29, 2024
Ajish Daniel we will investigate your reported behavior, it should work as you expect so there might be an issue with the calculation.
Log in to comment and vote
Comments3
Vidas
Nov 25, 2024
Ajish Daniel when we introduced SPI, we've got blocked on CPI because Teamhood does not have a dedicated default field for cost tracking. Maybe we should allow users to pick which field represents cost…
Maybe you have suggestions how should we do it? Because for planned value we can easily use budget, but factual/actual cost value is missing.
Ajish Daniel
Nov 26, 2024
Vidas You could introduce the actual cost field on the Gantt chart just like how I do it using custom fields for both Actual Cost and CPI.
However, one other thing that I have noticed that SPI is calculated based on actual start date and actual finish date in the schedule section. But if I start my activity earlier than the scheduled date and I have some progress on the task it won't show any SPI as well. Attached is the reference.
Vidas
Nov 29, 2024
Ajish Daniel we will investigate your reported behavior, it should work as you expect so there might be an issue with the calculation.