Gantt dependencies
Please add the ability to connect task start to start, end to end, start to end.
Currently you can only set it to end to start.
Also please add the ability to have lag/offset between tasks, so that how much time can / should be between the dependency end points.
Thanks!
Log in to comment and vote
Comments6
Harry Thakkar
Feb 17, 2025
Per the original comment, I don't see a way to add lag or offset yet. This is something I use regularly and would be nice to have available. Here is the microsoft project documentation on lag and lead time as a reference:
https://support.microsoft.com/en-us/office/add-lead-or-lag-time-to-a-task-692fde75-0734-47b6-a259-e87aa1a538f4
Vidas
Feb 23, 2025
Harry Thakkar: hey, lag / offset were descoped during development. We are still in the battle between keeping Gantt simple/light vs going full MS project scope. Nonetheless, we are working on improvements for Gantt constantly and will do few more early March, related to rescheduling and dependencies, just lag / offset will not be in scope. Sorry for now.
Oct 8, 2024
Oct 1, 2024
Aug 26, 2024
Giedrė | 2L
Jul 14, 2024
Gantt chart without these types of dependencies is basically non functional. Essential!