Skip to main content

Project progress based on project plan in portfolio report

TH has progress in Project Portfolio field which shows progress in Tasks. We need to see the project progress over time, i.e. whether the project is on time, behind schedule or ahead. We suggest adding an additional field "time", which would show the project progress over time. The progress bar would have different colours which would indicate whether the project is on time, behind schedule or ahead schedule (red, orange, green) and have % value. With this indicator we could easy see on Portfolio report progress in time and how much time is left per %. SPI index is OK but still we have to go to Timeline report and it show progress by Tasks. In general TH hasn't Time progress per Project or we can't find it :)

Status: Open3 comments

Log in to comment and vote

Comments3

  • Vidas

    Team•

    May 8, 2025

    One of the options is to show additional field in portfolio view, which would show:

    • If there are overdue tasks - how many days overdue from the earliest overdue task. "X days due"

    • If all tasks are on time - just on time label. "On Time"

    • If all tasks are on time and some are even ahead - how many days ahead by taking the latest task which is completed. "X days ahead"

    User can customize and show/hide this field. it would help to quickly identify more problematic projects among many.

  • Vidas

    Team•

    May 7, 2025

    Yes, only SPI shows if project is on time / behind or ahead. But you need to allocate budget to show SPI. In general this is a good suggestion. If I understand correctly - you are proposing to show "Progress %" field just like it's shown in Timeline, just have different coloring if it's ahead/on time/behind?

    • Giedrė | 2L

      •

      May 8, 2025

      Vidas not exactly. Timeline and Project portfolio shows progress of Tasks but non of them shows progress of Time which we need. We suggest add additional "Time progress" column to Project Portfolio which could indicate where we are in timeline (RED | ORANGE | GREEN).

      P.S.: In my opinion, the timeline report should also show not the progress of tasks, but the progress of time, due to the name "Timeline" :) Now we have hard-to-understand percentages in Timeline where tasks are not late in time, but the overall scope is lagging behind (see pictures)