Weekends and hollidays
If a task of 40h between a Monday and a Friday is moved to, for instance Wednesday, then the 40h are allocated in just 3 days (13h per day) from Wednesday to Friday. What I mean is that, as I seen it and as it is a 5-day task, if I move it to a Wednesday it should end the following Tuesday, not a Sunday, and keep a constant workload for the employee, unless I shrink it to three days on purpose.
Also, I wonder if it is possible to select national holidays (all employees) and other holidays for each employee (summer, other) so that the same happens when a task has to be split to jump from the beginning to the end of his/her holidays. I have spotted another feature request about the working calendar for each employee pointing in the same direction.
Log in to comment and vote
Comments2
Vidas
Jan 30, 2024
Now regarding duration - yes it is on our radar to improve this recalculation. We need to make schedule an editable field and make it fixed, so that if users performs changes, it is being respected on working days.
Vidas
Jan 30, 2024
Hey Pablo Barcelo national holidays is not part of Teamhood's features. But there exists a workaround - you could integrate with your Outlook calendar, and just make sure that you have a shared calendar which includes public holidays for your country. And lastly, just make sure in that calendar to have default status for each holiday as "Busy".