    We use teamhood to time block processes that don't need human input, but that dictate the scheduling as a whole. So having Sundays available as a working day, would be really helpful.

    Think a CNC machine running for two days unattended. Staff starts the process on a working day and will pick up the finished pieces on a working day. However, if we reschedule starting the machine on Friday teamhood will push the following item to Tuesday even though the machine would be finished on Monday.

  • prima prova

    •

    Jul 13, 2023

    M G how about to check if there re other similar requests before posting a new redundant one? the system suggests already on the side, so just having a look while typing wdnt be that bad. btw, pls see my april post (almost same title) and consider voting for it (and/or maybe Vidas can merge the two..?)

    • Vidas

      Team•

      Jul 13, 2023

      prima prova: merged, all good

  • Diego Villalobos

    •

    May 1, 2023

    Is possible to change working days on the Workload Report just by clicking on the Team member. May be this helps.

    • Isaac Patino

      •

      Apr 12, 2025

      I tried this out. You are indeed able to select a user's workdays and specify how many hours they work on each of those days individually. Unfortunately, those settings are not carried over to the Gantt view for those same users. It would be great if it did. It is the Gantt view that we use for planning and reporting.